A company is considering a project to improve its IT infrastructure. The project team wants to identify the assumptions, constraints, risks, and issues.
Categorize the assumption, constraint, risk, and issue correctly.
A. The unique server used by the team is out of service from 8:00 a.m. this morning.
B. Negotiations conducted last week by the management team with our partner resulted in an agreement to register a budget of US$50,000 in the next quarter for IT infrastructure upgrades to avoid this type of server failure.
C. The project may be delayed due to possible loss of data due to sudden shutdown of the server during its failure.
D. Development work on the main project deliverable is struggling to move forward due to the limited capacity of the current development infrastructure.